The IFCA datacenter suffered an unexpected shutdown, caused by a power cut due to a malfunctioning electrical installation. We are working hard on restoring the situation.
Please visit this page for more updates about the recovery process.
-
2014-05-15 14:32 CEST Grid Cluster is fully available.
-
2014-05-15 13:17 CEST GPFS storage is fully available.
All filesystems are now available.
-
2014-05-15 12:44 CEST GPFS storage partially available.
/gpfs/gaes
filesystem is not available. -
2014-05-15 12:44 CEST GRIDUI access is available.
GRIDUI cluster has been partially restored. There's no access to the batch system though.
-
2014-05-15 12:00 CEST Cloud infrastructure is recovered.
portal.cloud.ifca.es is now fully functional.
-
2014-04-14 18:00 CEST Power cut.
Due to a malfunctioning electrical installation the IFCA datacenter suffered an unexpected power cut. Only critical systems were restored.